Somerset was retained on this fast-track project to
provide erection stability analysis, erection sequencing and temporary
bracing design. This structure was the showcase at Expo 86.
The convention centre is approximately 1,000 feet
long and, together with the hotel, contained 10,000 metric tons
of structural steel. The hotel is 28 stories high with both field-welded
moment connections and braced bays. The convention hall is spanned
by 170 foot trusses. Steel erection took twelve months, after which
the roof sails were installed under a separate contract.
|

|