Somerset carried out the on-site construction engineering
for this key shut-down operation at Imperial Oil, involving the
major replacement of the catalytic regenerator head. Due to limited
access, we specified a 300 ton capacity ringer crane. The design
of all temporary structures, rigging and crane layouts was provided
by Somerset.
|


|